Hydraulic analysis · gravity conduction line

Vicampanavitz Conduction Line

New spring to new primary tank, Vicampanavitz, Nebaj, Quiché, Guatemala. Pipe sizing, head loss, pressure class, and valve layout on the total station survey, modeled in EPANET 2.2.

Pending · dry-season spring flow measurement
ProgramEWB-USC Guatemala
ElevationsTotal station survey, 95 stations
Date · revisionOct 27, 2026 · Rev B
Model files…_SURVEY_design_0.8Ls.inp
…_SURVEY_capacity_check.inp
1 · Result

2-inch PVC, with 2½-inch for the last 841 m

The survey puts the spring only 13.1 m above the tank site, about 11 m less than the satellite estimate. With the inlet 2.5 m above the tank floor, 10.6 m of drop is available. An all-2-inch line would use 9.7 m of it at 0.8 L/s, leaving 0.9 m: under the 1 m minimum, and below zero once the pipe ages. Switching the last 841 m (station 70 to the tank) to 2½-inch cuts the loss to 8.3 m and leaves 2.3 m, or 1.1 m with aged pipe, for about 10% more PVC.

Design flow0.8L/sBusiest day, year 2048
Head loss, spring to tank8.33m7.42 in 2″ + 0.91 in 2½″
Head available (surveyed)10.6m13.1 m drop − 2.5 m tank wall
Highest no-flow pressure172m245 psi at station 23
Two things to confirm before buying pipe

The model takes the spring box water level as the benchmark (station 1). If the water sits lower than the benchmark, subtract the difference from the 10.6 m. The dry-season spring flow is still unmeasured: if the spring gives 0.7 L/s or less, an all-2-inch line has enough margin (section 5).

2 · Survey

What the total station changed

The survey has 96 points. Station 2 ("North") is the orientation shot beside the benchmark and is not on the pipe, which leaves 95 points from the spring to the tank site. Every point lies within 30 m of the GPS track (half within 9 m), so the survey follows the same alignment.

Stations 72 to 83 were recorded out of route order, which makes the sheet's running total jump back and forth. The sheet totals 4,071 m; in route order the line is 3,050 m measured flat, matching the GPS track's 3,048 m, and 3,143 m along the ground, including the 2.5 m riser up the tank wall. The model uses the route order shown in the appendix.

Elevations stay in the survey's own datum, with the benchmark at 1000.000 m. The sheet's "GPS Elevation" column adds 1,558.199 m, the handheld GPS reading at the benchmark; that reading was about 43 m low, so treat the column as relative heights, not true altitude.

Three elevation sources, each measured from the spring. The satellite profile matched the survey in the valley (175 m deep against 172 m) but put the tank 11 m too low. The GPS heights scatter by tens of meters.
Key heights relative to the spring
PointTotal stationSatellite (SRTM)Handheld GPS
Valley bottom (lowest point each source found)−172.0 m (st. 23)−175 m−153 m
Tank site−13.1 m (st. 97)−24 m+23 m
3 · Design flow

0.8 L/s on the busiest day of 2048

Unchanged from Rev A. The line is sized for the whole community's busiest-day demand at the end of a 20-year design period, following Guatemalan rural water criteria (INFOM). If the spring gives less in the dry season, the line carries whatever the spring gives.

StepValueBasis
Households today × people each80 × 4.94Post-trip slides; Nebaj 2018 census (72,686 people, 14,708 households)
Population in 20486152.03 %/yr growth (INE projection) for 22 years; covers the 20 planned homes
Water per person90 L/dayTop of INFOM's 60–90 L/day range for homes with a tap
Busiest-day flow0.77 → 0.8 L/sAverage 0.64 L/s × 1.2, rounded up
4 · Head loss

How much drop each pipe size needs

Worked example: the recommended line at 0.8 L/s

  1. 2-inch section, 2,302 m. Water moves at 0.33–0.39 m/s. Hazen-Williams (C = 140) gives about 3.2 m of loss per km: 7.42 m including fittings.
  2. 2½-inch section, 841 m. The wider bore slows the water to 0.22 m/s, and the loss drops to about 1 m per km: 0.91 m including the exit into the tank.
  3. Total. 8.33 m used of 10.6 m available, so the inlet keeps 2.27 m of pressure. With aged pipe (C = 130) it keeps 1.07 m.

The available drop

Spring box water level (benchmark)1000.000 m
Tank site (station 97)986.896 m
Tank inlet, 2.5 m above the floor989.396 m
Available10.604 m

A layout works when its head loss plus 1 m of leftover pressure at the inlet fits inside this drop.

Drop each uniform pipe size needs (friction + fittings + 1 m at the tank), against the 10.6 m the survey found. All-2-inch needs 10.7 m at 0.8 L/s and just misses. The recommended mix needs 9.3 m.
Drop needed (m), uniform pipe size, 3,143 m. Green fits within 10.6 m.
Pipe0.5 L/s0.6 L/s0.7 L/s0.8 L/s1.0 L/sFull-open flow
5 · Options

Three ways to build it

All 2-inchRecommended mixAll 2½-inch

When all-2-inch is enough

  • Spring gives 0.7 L/s or less. At 0.7 L/s the inlet keeps 3.0 m (1.9 m with aged pipe).
  • Tank inlet 1.0 m above the tank site instead of 2.5 m (a half-buried tank). The inlet keeps 2.4 m (1.0 m aged), but the tank's water sits 1.5 m lower, so every home downhill gets 1.5 m less pressure.

Why the 2½-inch pipe goes at the tank end

Upsizing saves the same head wherever it goes, so it belongs where the larger pipe is cheapest. From station 61 to the tank the no-flow pressure stays under 72 m, so the 2½-inch pipe can be the thin-walled 160 psi class. Upsizing in the valley would mean thick 250 or 315 psi pipe.

6 · Recommended design

Pipe schedule and profile

Surveyed profile at 0.8 L/s. The blue hydraulic grade line stays above the ground the whole way, so the pipe runs full under pressure; the gap between them is the pressure in the pipe. The closest call is station 85, the high point 400 m before the tank, with 3.4 m. The strips show pipe class and pipe size.
Pipe schedule (ASTM D2241 PVC, 6 m lengths). Counts include 5% extra.
StationsSizeClassLengthNo-flow pressurePipes
S1 → S122″160 psi · SDR 26376 m0–86 m137
S61 → S702″160 psi · SDR 26401 m18–72 m
S12 → S202″250 psi · SDR 17197 m86–143 m232
S25 → S612″250 psi · SDR 171,127 m64–141 m
S20 → S25 (valley)2″315 psi · SDR 13.5200 m141–172 m36
S70 → tank2½″160 psi · SDR 26841 m11–45 m148
Total3,143 m553
Model results, recommended design
ResultNew pipe (C = 140)Aged pipe (C = 130)
Tank inlet pressure at 0.8 L/s2.27 m1.07 m
Lowest line pressure at 0.8 L/s3.4 m at station 85—
Highest line pressure at 0.8 L/s170.0 m (242 psi) at station 23—
Flow with the tank valve fully open0.91 L/s0.85 L/s
Flow at which the inlet drops to 0 m0.91 L/s. The line cannot carry 1.0 L/s; that would need all-2½-inch pipe.
7 · Checks

Sensitivity, water hammer, and velocity

Recommended design at 0.8 L/s under other assumptions
AssumptionHead lossInlet pressure
Hazen-Williams, C = 140 (design); hand calculation of the delivered file agrees8.33 m2.27 m
Darcy-Weisbach, PVC roughness 0.0015 mm8.2 m2.4 m
C = 150, new PVC (manufacturer's figure)7.4 m3.25 m
C = 130, aged pipe with biofilm9.5 m1.07 m

Water hammer

A pressure wave crosses the line and returns in about 15 seconds. Each class was chosen so no-flow pressure plus a sudden-closure spike at 0.7 m/s stays within the pipe's rating; the real full-open speed is only 0.44 m/s, which leaves extra margin.

ClassWave speedSpike at full flowMax no-flow allowed

Use gate valves, not quarter-turn ball valves, and close each over a minute or more.

Low velocity

At 0.8 L/s the water moves at 0.33–0.39 m/s in the 2-inch pipe and 0.22 m/s in the 2½-inch section, below the 0.6 m/s guides ask for to keep sediment moving. No size reaches 0.6 m/s with a 10.6 m drop, so handle sediment with a sand trap at the spring box, washouts at the low points, and periodic flushing with the tank valve wide open.

8 · Valves and crossings

Placed from the survey's high and low points

Main valves go at every high or low point that stands out by 5 m or more. The minor points stand out by 2.5–3.6 m; grade the trench to smooth them out, or add a valve if the ground won't allow it. Each valve must be rated for the no-flow pressure listed.

ValveStationDistanceElevationPressure, 0.8 L/sNo-flow
Crossings from the field notes. "EMPRIO" / "TERMRIO" read as river start and end, "TERPUENTE" as end of bridge, "TERMCAMINO" as end of road; confirm these with the survey crew.
CrossingStationsNo-flow pressureTreatment
River, valley bottomS22 → S23171–172 mGalvanized Schedule 40 steel where the pipe is exposed, anchored on both banks; washout at S23
RiverS31 → S32137–138 mGalvanized steel if exposed, or bury below scour depth with concrete cover
River and bridgeS56 → S57101–103 mGalvanized steel, strapped to the bridge or on its own supports; washout at S56
RoadS25, S3894–141 mBury deeper or run through a steel sleeve
Field road, trail, streetsS91 → S9432–35 mBury deeper or run through a sleeve
9 · Model files

Using the EPANET files

Vicampanavitz_conduction_SURVEY_design_0.8Ls.inp

Design run. SPRING is a reservoir at the benchmark (1000.000 m); TANK_IN draws 0.8 L/s at 989.396 m. Nodes are named by survey station (S3 to S96) and sit at their total station coordinates, so the EPANET map matches the survey.

Vicampanavitz_conduction_SURVEY_capacity_check.inp

Capacity run. TANK_IN becomes a free-discharge reservoir, and EPANET solves how much the line carries fully open. These two files replace the Rev A files built on satellite elevations.

  1. Open a file in EPANET 2.2 (free from the US EPA) and click Run.
  2. If the spring box water level differs from the benchmark, change the SPRING head.
  3. To test a different tank height, change the TANK_IN elevation; to test a flow, change its demand.
10 · Appendix

Method and station results

  • Solver: EPANET 2.2 engine, steady state, SI units. A separate hand calculation of the delivered file gives the same 8.33 m and 0.91 L/s.
  • Route order: each survey point placed by its position along the GPS track (the survey grid matches the GPS track to within 1.5° of rotation).
  • Pipe lengths: 3D distance between consecutive stations, plus a 2.5 m riser at the tank.
  • Friction: Hazen-Williams, C = 140; fittings K = 0.3 per pipe, plus entrance 0.5, two gate valves 0.2 each, exit 1.0.
  • Pressure class: no-flow pressure plus a sudden-closure spike at 0.7 m/s within the ASTM D2241 rating. A 124 m stretch (S39–S46) that could take 160 psi is folded into the surrounding 250 psi run to keep the schedule simple.
  • Inside diameters (Amanco Wavin): 2″ 55.70 / 53.21 / 51.38 mm and 2½″ 67.44 mm for 160 / 250 / 315 psi.
Station-by-station results, recommended design at 0.8 L/s (95 rows)
StationDistance (km)Elevation (m)Grade line (m)Pressure (m)psiNo-flow (m)Pipe inField note
Sources

References