Guatemala Water Pipeline
Spring water to a village tank, 3.1 km downhill, with gravity doing all the work.
- Revision
- Rev B · October 2026
- Team
- EWB-USC Guatemala
- Location
- Vicampanavitz, Nebaj, Quiché
- Model
- EPANET 2.2 · 95-station survey
Sized for the busiest day of 2048.
Engineers Without Borders USC is working with Vicampanavitz, a community of about 80 households in Nebaj, Guatemala, on a new conduction line from a spring to a primary tank. There is no pump: the line drops 172 m into a river valley and climbs back out to a tank site only 13.1 m below the spring.
Fitting the pipe to the drop.
I modeled the line in EPANET 2.2 on our team’s 95-station total station survey to choose pipe sizes and pressure classes. The survey found 11 m less drop than the satellite estimate, which left an all-2-inch line just short of the 1 m minimum pressure at the tank. The design keeps 2-inch PVC for most of the route and switches to 2½-inch for the last 841 m, which uses about 10% more PVC and leaves 2.3 m of pressure at the inlet.
- 3,143 m
- of PVC from the spring to the tank, measured along the ground
- 0.8 L/s
- design flow: the busiest day for a projected 615 people in 2048
- 8.33 m
- of head loss, inside the 10.6 m of drop the survey found
- 245 psi
- highest no-flow pressure, at the valley bottom (172 m of head)
- A pipe schedule in 160, 250, and 315 psi PVC classes: 553 six-meter lengths, ordered by pressure zone.
- Air valves, washouts, and river and road crossings placed from the survey’s high and low points.
- Checked against aged pipe, Darcy-Weisbach friction, water hammer, and sediment velocity.
Rev B design on the total station survey. Still pending a dry-season spring flow measurement and a check of the spring box water level; the line has not been built yet.